City begins Transit Center repairs but won’t set reopening date

“Repairs are scheduled to be complete by the first week of June 2019.”

The Transbay Joint Powers Authority (TJPA) announced Friday that repairs will finally begin on the Transbay Transit Center, more than four months after mysteriously cracked support beams shuttered the barely-used, $2.2 billion downtown facility.

According to Friday’s statement:

Early morning Saturday, February 2, 2019 , crews will replace the hydraulic jacks on First Street with a shoring system to allow the TJPA to reinforce the girders on the bus deck above First Street.

[…] Steel plates are currently being fabricated offsite and will be delivered to the transit center in March for installation. Repairs are scheduled to be complete by the first week of June 2019 and then the shoring systems at both Fremont and First streets will be removed.

 

Read more at Curbed SF

 

 